What will you do if the client asked for more features and you are already behind schedule

Respuesta

Respuesta de la entrevista

1 respuesta

19

If they ask for more features beyond what's in the agreed upon contract SOW and requirements, then you'll have to renegotiate the project cost and schedule. As for you being currently behind schedule, you always have to manage your customer/stakeholder expectations. They should know you are behind schedule, what your doing to get back on track, or why getting back on track is not possible.